|
Oftentimes a construction contractor will have multiple contracts on
a single project, such as a single contract with the Owner and several
with subcontractors. In the event of a dispute, the contract determines
the type of dispute resolution. If these contracts contain differing
dispute resolution provisions, the contractor may find itself at a
great disadvantage.
Litigation may be the only choice when multiple parties are involved
in a complex dispute. To avoid unnecessary duplication of efforts by
courts and litigants, state and federal civil rules of procedure are
already designed to handle multiple-party litigation, and can bring all
third parties and claims into one lawsuit. Recently there has been a
movement away from litigation to other forms of dispute resolution such
as arbitration. However, due to its voluntary nature, arbitration is
not set up to consolidate claims or force third parties into the
arbitration proceedings.
So what is arbitration? Arbitration is a legal alternative to
litigation whereby the parties to a dispute agree to submit their
respective positions to a neutral third party (the arbitrator) for
dispute resolution. The agreement between the parties to submit their
dispute to arbitration is a legally binding contract. All arbitral
decisions are considered to be "final and binding."
Idaho adopted the Uniform Arbitration Act in 1975 and codified it as
Title 7, Chapter 9 of the Idaho Code. In practice arbitration is
generally used as a substitute for judicial systems, particularly when
the judicial processes are viewed as too slow, expensive, or biased.
A business having multiple contracts on a single project should
ensure that the method of dispute resolution outlined in the contracts
is consistent. An interesting example of problems that occur when
inconsistent dispute resolution provisions are contained in multiparty
contracts is found in the construction industry. The owner of a
construction project may contract with several different parties
including contractors, design professionals, and or construction
managers to perform work and provide services on the project. Each of
these individual contracts may contain different dispute resolution
procedures. For instance, the owner might have a contract with the
construction manager on the project that requires all claims and
disputes on the project be submitted to arbitration. The owner might
then have a separate contract with the general contractor that has no
arbitration agreement and instead allows the parties to litigate any
claims or dispute on the project. Recently, I was involved in such a
situation where I was representing the construction manager, and this
is what transpired. The contractor filed suit against the owner
alleging breach of contract for unpaid money allegedly owed to the
contractor. The owner counterclaimed against the contractor alleging
defective work and delay damages on the project. The owner then filed
suit against the construction manager for breach of contract and
indemnification alleging that the construction manager failed to
properly supervise the contractor's work. However, the contract between
the owner and construction manager contained an arbitration clause
mandating that the parties arbitrate any claim or dispute on the
project. In spite of this arbitration provision the owner filed suit
against the construction manager, and then filed a motion to
consolidate seeking to join the construction manager into the pending
lawsuit with the contractor.
How will a court interpret the arbitration agreement between the
construction manager and the owner? How should a court reconcile the
arbitration agreement with the other pending litigation?
There is no question that in Idaho arbitration agreements between
parties will be enforced. However, Idaho courts have not fully
addressed the issues presented by an arbitration agreement in the
context of multi-party litigation. Although arbitration is generally
encouraged by the courts because it expedites the settlement of
disputes simply, clearly and inexpensively, in the context of
multi-party litigation the opposite can be true. Parties may be forced
to duplicate time and costs in two separate proceedings and face the
very real possibility of inconsistent judgments between the arbitration
and litigation proceedings.
The U.S. Supreme Court has generally held that arbitration must be
allowed to proceed even if it would result in the possibility of
inefficient maintenance of separate proceedings in different forums and
result in "piecemeal" resolution of disputes.
Getting back to my example cited above, ultimately the district
court denied the owner's motion to consolidate, and granted the
construction manager's motion to stay the proceedings pending
arbitration. The result was that the owner had to simultaneously
prepare for trial against the contractor AND arbitrate its claims
against the construction manager.
If a business is involved in a complex transaction or project with
multiple third parties, it would be wise to maintain consistency in the
arbitration language of all its contracts, and steer clear of a
situation where the business has arbitration agreements with some, but
not all, of the parties involved. The business should have its
attorneys review all the contracts' dispute resolution language before
the contracts are executed.
Paul A. Boice is an associate with the law firm Meuleman Mollerup LLP
practicing in the areas of commercial litigation, wills, trust, and
probate. Mr. Boice returned to Idaho recently from a year of duty
serving with the US Army 116th Brigade Combat Team in Iraq. Mr. Boice
can be reached at 208.342.6066, or by email
This e-mail address is being protected from spam bots, you need JavaScript enabled to view it
; more information at www.lawidaho.com.
|