|
(Published in the Idaho Business Review, May 2006)
A
recent Idaho Supreme Court case has extended protection for contractors
against negligence suits when a project turns out defective. In Craig Johnson Construction v. Floyd Town Architects,
the Idaho Supreme court held that a contractor is not liable in a
negligence suit when construction was in accordance with plans produced
by the owner and/or its architect.
In Johnson, a contractor built a number of condominiums in Ketchum.
Due to insufficient venting and improper insulation, the surfaces of
the roofs over the ceilings of the condominiums were warmer than the
roof surface over the rafters. When snow melted and slid down the roof
over the ceilings, it would hit the colder portion of the roof over the
rafters, re-freeze and cause a condition known as an ice dam. Snow melt
from the roof would then accumulate and leak inside the condominiums,
causing almost a half million dollars in damage.
When the homeowners sued the contractor for negligence, the
contractor claimed he should be free from liability because he followed
the plans and specifications produced by an architect hired by the
developer. Agreeing with the contractor's position, the Supreme Court
announced a new rule that contractors on a private project cannot be
liable for negligence if they reasonably rely on, and follow, plans and
specifications prepared by the owner and/or its architect.
Unfortunately for the contractor in Johnson, it appeared he failed to
follow the plans and, thus, was not entitled to protection under the
rule. Nonetheless, all contractors gained some additional levels of
protection from liability as a result of this case.
Idaho has long recognized that a contractor who follows plans
prepared by or on behalf of the owner is not liable to the owner for
breach of contract if the project is defective. Since the 1960's, Idaho
has also prohibited negligence suits against contractors on public
works projects. However, until the Johnson case this prohibition had
not been extended to private projects.
The rule does, however, have exceptions, and contractors should be
careful to understand how and when they can lose liability protection.
First, this defense is only available to contractors who actually
follow the plans and specifications. In many cases, the contractor on
its own decides there is a fault in the plans and implements a fix
without consulting the owner or architect. In the event the fix makes
the problem worse or does not solve the problem, the contractor is once
again subject to liability. If it appears the plans are defective, the
contractor should insist that the architect and owner produce revisions
to the plans. The contractor should make requests for clarification in
writing and insist that the fix prepared by the architect be issued as
a written change order. When there is no fix forthcoming or the
proposed fix appears insufficient, the contractor should contact an
attorney for advice.
Second, the contractor should be mindful that it may not rely on
plans and specifications if it knows or should have known that the
plans are defective. For instance, a contractor in McCall or Sun Valley
is likely charged with knowing which designs are effective in
preventing ice dams like those in the Johnson case. If such a
contractor is presented with plans drawn by an architect from sunny
Arizona which do not address the ice dam issue, the contractor should
draw the architect's attention to the condition and insist the drawings
be revised. Other potential traps exist when owners provide a "builders
set" of plans, which are commonly the bare minimum required to obtain a
building permit. In such a case it is possible the plans may be too
minimal for the contractor to rely upon. In this instance, the
contractor should insist on a more comprehensive set of plans. If this
is not possible the contractor may consider including the cost of
hiring its own architect in its bid, but by doing so the contractor may
lose the protection of the rule set forth in Johnson. However, by
hiring its own architect a contractor may reduce the risk of defects.
Finally, contractors should be cautious in entering into a
"design-build" project where the contractor hires the architect and
designs the project. While the Johnson decision seems to imply the
contractor is shielded from negligence suits in such a case, it is
possible its contract with the architect will contain a provision which
requires the contractor to indemnify the architect for negligence
claims. While it is not clear such indemnification provisions are
enforceable, a contractor would be sorely disappointed to escape
liability under the new rule, only to have to indemnify the architect's
negligence pursuant to a contract provision with the architect.
If a contractor has questions regarding its protection against a
negligence suit, the contractor should consult its attorney for an
evaluation of the contractor's liability.
Mike Baldner, a partner with the law firm Meuleman Mollerup LLP, is a
real estate lawyer focusing on complex high value real estate
transactions. He represents clients ranging from corporate tenants,
developers, landlords, sellers, lenders, and title companies. Mr.
Baldner can be reached at 208.342.6066 or by email at
This e-mail address is being protected from spam bots, you need JavaScript enabled to view it
. more information at www.lawidaho.com.
|