(Published by the
Idaho Business Review, July 2009)
An award for consequential
damages against a contractor can turn a profitable project into a potential for
bankruptcy.Consider this example:In 1983 a contractor was hired as construction
manager on a project to renovate an Atlantic
City casino.The contract stated that the contractor would coordinate with the owner
and architect, supervise the trade contractors, and set a guaranteed maximum
price for the project in exchange for a fee and expenses.
Although a great deal of
the project was completed on time, construction of the façade designed to
attract customers passing by the casino was late.The owner terminated the contract because of
the delay on the façade, and the contractor brought an action for wrongful
termination and the balance of the fee.In turn, the casino sought damages for lost profits and was awarded
$14,500,000 in arbitration which was later upheld by the New Jersey Supreme
Court.This scenario demonstrates the
impact of a consequential damage award and illustrates the importance of
contractually managing these risks.
The American Institute of
Architects' (AIA) form contract language pertaining to consequential damages is
contained in the general conditions (AIA A201).The A201 general conditions adopted a mutual waiver of consequential
damages in reaction to the decision referenced above.The pertinent section reads as follows:
"The Contractor and Owner waive all
claims against each other for all consequential damages arising out of or
relating to this Contract. This mutual waiver includes:
Damages incurred by the Owner for:
oRental expenses;
oFor losses of use, income, profit,
financing, business and reputation; and
oFor loss of management or employee
productivity or of the services of such persons; and
Damages incurred by the Contractor for
oPrincipal
office expenses including the compensation of personnel stationed there;
oFor
losses of financing, business and reputation; and
oFor
loss of profit except anticipated profit arising directly from the Work."
This mutual waiver is
applicable, without limitation, to all consequential damages due to either
party's termination. Nothing contained
in this shall be deemed to preclude an award of liquidated damages, when
applicable, in accordance with the requirements of the Contract Documents.
On
its face, this language seems to favor contractors because the largest
consequential damage claims (like the one referenced above) are those
recoverable by owners.Lost profits may
be recoverable by contractors, but typically those losses are not comparatively
as large.
Contractors should also be
aware that the A201 mutual waiver of consequential damages language may not preclude
owners from recovering consequential damages for construction delays.Owners may also still recover lost profits,
loss of use or other consequential damages as liquidated damages even if the
parties agree to the mutual waiver of consequential damages.The A201 document removes "liquidated
damages" from the waiver of "consequential damages."
In Idaho, two requirements must be met for
recovery of liquidated damages: (1) an accurate determination of the
actual damages that might be incurred upon breach must be difficult or
impossible to determine; and (2) the amount of the liquidated damages must bear
a reasonable relationship to the actual damages anticipated to be
incurred.
Liquidated damages are somewhat
beneficial to contractors in that they limit the risk resulting from
construction delays.Contractors should
discuss what types of costs a liquidated damages provision is intended to cover
when negotiating contract terms with an owner and try to limit the recoverable amount
to direct damages.
Additionally, contractors should
consider including a liquidated damage provision which applies in the case of
owner-caused delays and disruptions.This
way contractors may recover for those overhead, bonding capacity, and onsite
costs which continue to be incurred as a project is delayed.While the drastic results of an award of
consequential damages have been addressed by A201.The parties may still choose to include a liquidated
damage provision which attempts to address delay damages.
Contractors should consider having
their legal consultant periodically review their contracts to manage their risk
exposure in the contract's liquidated damage provisions and in language pertaining to consequential damages.
For more information contact us at: Meuleman Mollerup LLP
755 W Front Street, Suite 200 · Boise, ID 83702-5802 · Phone (208) 342-6066 Fax (208) 336-9712
e-mail: lawfirm@lawidaho.com